Outage history · 172 outages
This list as a CSV file, one row per outage, times in UTC.
SallinsFault
60 customers affected · began Fri 25 Sep, 12:04 · expected back by 17:00 (about 5 h) · no restore time published
SallinsPlanned · new connections
38 customers affected · began Thu 24 Sep, 12:55 · listed for about 2 h 30 min · no end time published
AthyPlanned · supply quality
39 customers affected · began Thu 24 Sep, 09:31 · listed for about 6 h 30 min · no end time published
KildareFault
22 customers affected · began Tue 22 Sep, 20:18 · restored 22:31 (2 h 13 min)
NaasPlanned · network upgrade
34 customers affected · began Tue 22 Sep, 14:05 · listed for about 1 h · no end time published
DunfirthPlanned · network upgrade
104 customers affected · began Tue 22 Sep, 10:05 · scheduled until 17:00 (6 h 55 min)
SallinsPlanned · supply quality
26 customers affected · began Tue 22 Sep, 09:47 · listed for about 5 h · no end time published
CelbridgePlanned · supply quality
32 customers affected · began Tue 22 Sep, 08:59 · scheduled until 17:00 (8 h 1 min)
DunfirthPlanned · supply quality
120 customers affected · began Mon 21 Sep, 12:18 · scheduled until 17:00 (4 h 42 min)
MoneycooleyPlanned · line diversion
85 customers affected · began Mon 21 Sep, 11:22 · scheduled until 17:00 (5 h 38 min)
CelbridgePlanned · supply quality
48 customers affected · began Mon 21 Sep, 10:21 · listed for about 6 h · no end time published
DunfirthPlanned · supply quality
19 customers affected · began Mon 21 Sep, 10:20 · listed for about 5 h · no end time published
KilcullenFault
48 customers affected · began Sun 20 Sep, 08:46 · restored 10:58 (2 h 12 min) · 13 min later than ESB estimated
NaasFault
1,278 customers affected · began Sat 19 Sep, 08:46 · restored 09:03 (17 min) · 57 min earlier than ESB estimated
KilcullenFault
48 customers affected · began Fri 18 Sep, 21:07 · restored 23:48 (2 h 41 min) · 48 min later than ESB estimated
SallinsPlanned
42 customers affected · began Fri 18 Sep, 10:21 · listed for about 5 h 30 min · no end time published
CelbridgePlanned · new connections
56 customers affected · began Fri 18 Sep, 10:00 · listed for about 5 h · no end time published
SallinsFault
42 customers affected · began Fri 18 Sep, 08:52 · expected back by 11:45 (about 3 h) · no restore time published
KilcockFault
11 customers affected · began Thu 17 Sep, 19:05 · restored 22:55 (3 h 50 min) · 1 h 10 min later than ESB estimated
JohnstownFault
68 customers affected · began Thu 17 Sep, 11:28 · off for about 1 h 30 min · no restore time published
KildareFault
10 customers affected · began Thu 17 Sep, 10:35 · restored 12:24 (1 h 49 min) · 51 min earlier than ESB estimated
Repeat fault - outage 2 of 2 at this location in quick succession
KildareFault
10 customers affected · began Thu 17 Sep, 10:15 · restored 10:35 (20 min) · 1 h 55 min earlier than ESB estimated
Repeat fault - outage 1 of 2 at this location in quick succession
NaasPlanned · network upgrade
19 customers affected · began Thu 17 Sep, 09:17 · listed for about 2 h 30 min · no end time published
KildareFault
49 customers affected · began Wed 16 Sep, 23:19 · restored Thu 17 Sep, 01:02 (1 h 43 min) · 58 min earlier than ESB estimated
KildareFault
18 customers affected · began Wed 16 Sep, 23:16 · restored Thu 17 Sep, 09:33 (10 h 17 min) · 2 h 27 min earlier than ESB estimated
- Outage began · 18 customers
- 16 customers still off
- Supply restored
KildareFault
131 customers affected · began Wed 16 Sep, 21:20 · off for under 30 min · no restore time published
KildareFault
87 customers affected · began Wed 16 Sep, 21:17 · off for about 30 min · no restore time published
KildareFault
81 customers affected · began Wed 16 Sep, 21:15 · off for about 30 min · no restore time published
KildareFault
49 customers affected · began Wed 16 Sep, 21:13 · off for about 30 min · no restore time published
KildareFault
106 customers affected · began Wed 16 Sep, 21:08 · off for about 30 min · no restore time published
KildareFault
55 customers affected · began Wed 16 Sep, 21:07 · off for about 30 min · no restore time published
KildareFault
97 customers affected · began Wed 16 Sep, 21:05 · off for about 30 min · no restore time published
KildareFault
1,129 customers affected · began Wed 16 Sep, 21:03 · restored 21:48 (45 min) · 3 h 42 min earlier than ESB estimated
KildareFault
2,013 customers affected · began Wed 16 Sep, 19:02 · restored 23:12 (4 h 10 min) · 48 min earlier than ESB estimated
- Outage began · 2,013 customers
- 208 customers still off
- Supply restored
AthyFault
38 customers affected · began Wed 16 Sep, 12:33 · restored 14:37 (2 h 4 min) · 38 min earlier than ESB estimated
AthyFault
1,523 customers affected · began Wed 16 Sep, 12:04 · restored 14:57 (2 h 53 min) · 1 h 3 min earlier than ESB estimated
- Outage began · 1,523 customers
- 1,173 customers still off
- Supply restored
MonreadPlanned · supply quality
196 customers affected · began Wed 16 Sep, 09:25 · scheduled until 17:00 (7 h 35 min)
BlakePlanned · supply quality
46 customers affected · began Tue 15 Sep, 09:55 · scheduled until 17:00 (7 h 5 min)
NaasPlanned · network upgrade
13 customers affected · began Tue 15 Sep, 09:21 · listed for about 1 h 30 min · no end time published
AthyPlanned · supply quality
113 customers affected · began Tue 15 Sep, 09:19 · listed for about 6 h · no end time published
KilcullenFault
48 customers affected · began Mon 14 Sep, 17:32 · restored 19:03 (1 h 31 min) · 27 min earlier than ESB estimated
AthyPlanned · supply quality
21 customers affected · began Mon 14 Sep, 10:31 · listed for about 5 h 30 min · no end time published
MonreadPlanned · supply quality
52 customers affected · began Mon 14 Sep, 10:00 · scheduled until 17:00 (7 h)
JohnstownPlanned · network upgrade
22 customers affected · began Mon 14 Sep, 09:31 · listed for about 3 h · no end time published
KildareFault
22 customers affected · began Sun 13 Sep, 20:27 · restored 22:53 (2 h 26 min) · 8 min later than ESB estimated
KildareFault
85 customers affected · began Fri 11 Sep, 11:19 · expected back by 17:00 (about 5 h 30 min) · no restore time published
BlessingtonFault
12 customers affected · began Thu 10 Sep, 22:28 · restored Fri 11 Sep, 01:52 (3 h 24 min) · 8 min earlier than ESB estimated
LeixlipPlanned
140 customers affected · began Thu 10 Sep, 10:37 · scheduled until 17:00 (6 h 23 min)
KilcullenPlanned · supply quality
89 customers affected · began Wed 9 Sep, 12:28 · scheduled until 18:30 (6 h 2 min)
SallinsFault
38 customers affected · began Wed 9 Sep, 10:11 · restored 12:37 (2 h 26 min) · 37 min later than ESB estimated
SallinsPlanned · supply quality
162 customers affected · began Wed 9 Sep, 09:45 · scheduled until 17:00 (7 h 15 min)
MonreadFault
123 customers affected · began Tue 8 Sep, 20:18 · restored Thu 10 Sep, 12:40 (40 h 22 min) · 19 h 25 min later than ESB estimated
- Outage began · 123 customers
- 10 customers still off
- Supply restored
BlakePlanned · new connections
32 customers affected · began Tue 8 Sep, 12:27 · listed for about 3 h 30 min · no end time published
AthgarvanPlanned
97 customers affected · began Tue 8 Sep, 11:42 · listed for about 5 h · no end time published
KilcullenPlanned · new connections
43 customers affected · began Tue 8 Sep, 11:41 · scheduled until 16:00 (4 h 19 min)
SallinsPlanned · supply quality
21 customers affected · began Tue 8 Sep, 08:58 · listed for about 4 h · no end time published
NaasFault
481 customers affected · began Tue 8 Sep, 02:16 · restored 02:19 (3 min) · 1 h 11 min earlier than ESB estimated
NaasFault
77 customers affected · began Tue 8 Sep, 00:56 · restored 01:03 (7 min) · 57 min earlier than ESB estimated
NaasFault
20 customers affected · began Mon 7 Sep, 19:04 · off for about 2 h · no restore time published
NaasFault
404 customers affected · began Mon 7 Sep, 19:03 · restored Tue 8 Sep, 02:16 (7 h 13 min) · 3 h 46 min later than ESB estimated
- Outage began · 25 customers
4 further updates
- 174 customers still off
- 216 customers still off
- 404 customers still off
- 217 customers still off
- Supply restored
CelbridgeFault
14 customers affected · began Mon 7 Sep, 15:53 · restored 20:11 (4 h 18 min) · 1 h 11 min later than ESB estimated
DunfirthFault
337 customers affected · began Mon 7 Sep, 11:20 · restored 13:00 (1 h 40 min) · 30 min later than ESB estimated
- Outage began · 301 customers
2 further updates
- 337 customers still off
- 332 customers still off
- Supply restored
EdenderryPlanned · supply quality
130 customers affected · began Mon 7 Sep, 10:08 · scheduled until 16:00 (5 h 52 min)
SallinsPlanned · supply quality
70 customers affected · began Mon 7 Sep, 09:50 · scheduled until 17:00 (7 h 10 min)
JohnstownFault
68 customers affected · began Sun 6 Sep, 18:53 · restored 21:32 (2 h 39 min) · 58 min earlier than ESB estimated
DunfirthFault
268 customers affected · began Sun 6 Sep, 10:45 · restored 14:01 (3 h 16 min) · 2 h 59 min earlier than ESB estimated
KilcullenFault
11 customers affected · began Fri 4 Sep, 14:25 · restored 15:26 (1 h 1 min) · 1 h 4 min earlier than ESB estimated
KilcockFault
110 customers affected · began Fri 4 Sep, 11:09 · restored 12:58 (1 h 49 min) · 43 min later than ESB estimated
DunfirthPlanned · supply quality
36 customers affected · began Fri 4 Sep, 10:29 · scheduled until 17:00 (6 h 31 min)
MonreadFault
12 customers affected · began Fri 4 Sep, 09:44 · restored 19:42 (9 h 58 min) · 2 h 42 min later than ESB estimated
NaasPlanned · supply quality
16 customers affected · began Fri 4 Sep, 09:23 · listed for about 3 h · no end time published
AthyFault
16 customers affected · began Fri 4 Sep, 08:12 · restored 09:25 (1 h 13 min) · 50 min earlier than ESB estimated
BlakeFault
32 customers affected · began Thu 3 Sep, 14:41 · off for about 1 h 30 min · no restore time published
BlakeFault
22 customers affected · began Thu 3 Sep, 14:34 · restored 16:16 (1 h 42 min) · 2 h 14 min earlier than ESB estimated
MorristownFault
21 customers affected · began Thu 3 Sep, 11:58 · off for about 5 h 30 min · no restore time published
BlakePlanned · supply quality
26 customers affected · began Thu 3 Sep, 11:34 · listed for about 2 h · no end time published
MoneycooleyPlanned · new connections
11 customers affected · began Thu 3 Sep, 09:57 · listed for about 6 h · no end time published
MorristownFault
13 customers affected · began Wed 2 Sep, 15:55 · restored 19:01 (3 h 6 min) · 1 h 29 min earlier than ESB estimated
DunfirthPlanned · network upgrade
77 customers affected · began Wed 2 Sep, 10:03 · listed for about 5 h · no end time published
JohnstownPlanned · supply quality
18 customers affected · began Wed 2 Sep, 09:20 · listed for about 5 h 30 min · no end time published
KildarePlanned
66 customers affected · began Wed 2 Sep, 09:05 · listed for about 6 h · no end time published
DunfirthPlanned · supply quality
120 customers affected · began Tue 1 Sep, 17:28 · listed for about 30 min · no end time published
KildarePlanned · new connections
30 customers affected · began Tue 1 Sep, 12:21 · listed for about 3 h 30 min · no end time published
BlakeFault
31 customers affected · began Tue 1 Sep, 10:36 · restored 22:00 (11 h 24 min)
MoneycooleyFault
21 customers affected · began Tue 1 Sep, 10:17 · off for about 13 h 30 min · no restore time published
BlessingtonPlanned · supply quality
54 customers affected · began Tue 1 Sep, 09:42 · listed for about 6 h 30 min · no end time published
NaasPlanned
26 customers affected · began Tue 1 Sep, 09:01 · scheduled until 17:00 (7 h 59 min)
MacetownPlanned · supply quality
20 customers affected · began Mon 31 Aug, 10:14 · listed for about 6 h · no end time published
CelbridgeFault
48 customers affected · began Sat 29 Aug, 18:58 · restored 19:17 (19 min) · 1 h 28 min earlier than ESB estimated
KildareFault
1,080 customers affected · began Fri 28 Aug, 13:19 · off for under 30 min · no restore time published
KilcullenPlanned · supply quality
12 customers affected · began Fri 28 Aug, 09:59 · scheduled until 17:00 (7 h 1 min)
CelbridgePlanned · network upgrade
11 customers affected · began Fri 28 Aug, 09:49 · listed for about 6 h · no end time published
NaasPlanned · supply quality
29 customers affected · began Fri 28 Aug, 09:44 · listed for about 5 h 30 min · no end time published
NaasPlanned · supply quality
13 customers affected · began Thu 27 Aug, 11:11 · scheduled until 17:00 (5 h 49 min)
AthyPlanned · supply quality
22 customers affected · began Thu 27 Aug, 11:04 · listed for about 4 h · no end time published
CelbridgePlanned · network upgrade
76 customers affected · began Thu 27 Aug, 10:15 · listed for about 6 h 30 min · no end time published
KilcullenPlanned · supply quality
162 customers affected · began Wed 26 Aug, 11:23 · scheduled until 17:00 (5 h 37 min)
MoneycooleyFault
147 customers affected · began Wed 26 Aug, 09:36 · expected back by 17:00 (about 7 h 30 min) · no restore time published
Repeat fault - outage 2 of 2 at this location in quick succession
- Outage began · 37 customers
- 147 customers still off
- Estimated restore, from ESB
MoneycooleyFault
147 customers affected · began Wed 26 Aug, 09:15 · restored 09:28 (13 min) · 3 h 2 min earlier than ESB estimated
Repeat fault - outage 1 of 2 at this location in quick succession
KilcullenPlanned · supply quality
11 customers affected · began Tue 25 Aug, 10:41 · scheduled until 17:00 (6 h 19 min)
CelbridgePlanned · supply quality
134 customers affected · began Tue 25 Aug, 10:02 · listed for about 6 h 30 min · no end time published
LeixlipPlanned · supply quality
199 customers affected · began Tue 25 Aug, 09:00 · listed for about 7 h · no end time published
KilcullenPlanned · supply quality
12 customers affected · began Mon 24 Aug, 09:02 · listed for about 5 h · no end time published
BaltinglassFault
18 customers affected · began Sat 22 Aug, 18:28 · restored 20:48 (2 h 20 min) · 1 h 57 min earlier than ESB estimated
KildareFault
22 customers affected · began Fri 21 Aug, 21:09 · restored 23:43 (2 h 34 min) · 12 h 32 min earlier than ESB estimated
KilcockFault
109 customers affected · began Fri 21 Aug, 19:40 · restored Sat 22 Aug, 09:15 (13 h 35 min) · 4 h 45 min earlier than ESB estimated
MoneycooleyFault
13 customers affected · began Thu 20 Aug, 12:53 · expected back by 17:00 (about 4 h) · no restore time published
MoneycooleyPlanned
16 customers affected · began Thu 20 Aug, 12:32 · scheduled until 17:00 (4 h 28 min)
SallinsPlanned · new connections
33 customers affected · began Thu 20 Aug, 10:44 · listed for about 4 h 30 min · no end time published
SallinsPlanned · network upgrade
25 customers affected · began Thu 20 Aug, 09:41 · listed for about 6 h 30 min · no end time published
NaasPlanned · supply quality
23 customers affected · began Thu 20 Aug, 09:33 · listed for about 2 h 30 min · no end time published
KilcullenPlanned · new connections
16 customers affected · began Wed 19 Aug, 12:55 · listed for about 2 h · no end time published
LeixlipFault
1,892 customers affected · began Wed 19 Aug, 09:44 · restored 10:53 (1 h 9 min) · 8 min later than ESB estimated
NaasFault
2,327 customers affected · began Wed 19 Aug, 09:12 · restored 11:41 (2 h 29 min) · 1 h 4 min earlier than ESB estimated
- Outage began · 2,327 customers
- 92 customers still off
- Supply restored
MorristownPlanned · network upgrade
195 customers affected · began Tue 18 Aug, 10:10 · listed for about 6 h 30 min · no end time published
BlakeFault
17 customers affected · began Tue 18 Aug, 09:08 · restored 19:04 (9 h 56 min) · 3 h 4 min later than ESB estimated
KildareFault
61 customers affected · began Mon 17 Aug, 12:47 · restored 14:14 (1 h 27 min) · 1 h 46 min earlier than ESB estimated
AthyPlanned · new connections
33 customers affected · began Mon 17 Aug, 12:46 · scheduled until 16:00 (3 h 14 min)
SallinsPlanned · network upgrade
25 customers affected · began Mon 17 Aug, 10:19 · listed for about 5 h 30 min · no end time published
SallinsPlanned · supply quality
38 customers affected · began Mon 17 Aug, 10:18 · listed for about 6 h · no end time published
AthyPlanned · network upgrade
129 customers affected · began Mon 17 Aug, 09:30 · scheduled until 16:30 (7 h)
AthyPlanned · supply quality
21 customers affected · began Mon 17 Aug, 09:26 · listed for about 5 h 30 min · no end time published
KildareFault
22 customers affected · began Fri 14 Aug, 18:55 · restored 21:34 (2 h 39 min) · 2 h 11 min earlier than ESB estimated
DunfirthFault
1,525 customers affected · began Fri 14 Aug, 09:12 · restored 09:32 (20 min) · 43 min earlier than ESB estimated
- Outage began · 1,525 customers
2 further updates
- 591 customers still off
- 182 customers still off
- Supply restored
MorristownPlanned · new connections
252 customers affected · began Thu 13 Aug, 12:15 · scheduled until 17:00 (4 h 45 min)
KilcullenPlanned · supply quality
227 customers affected · began Thu 13 Aug, 12:11 · scheduled until 17:00 (4 h 49 min)
NaasPlanned · supply quality
26 customers affected · began Thu 13 Aug, 09:36 · listed for about 7 h · no end time published
AthgarvanPlanned · line diversion
332 customers affected · began Thu 13 Aug, 09:29 · scheduled until 17:00 (7 h 31 min)
KilcullenPlanned · supply quality
19 customers affected · began Wed 12 Aug, 13:40 · listed for about 2 h 30 min · no end time published
MorristownFault
140 customers affected · began Wed 12 Aug, 13:34 · restored 16:34 (3 h)
SallinsPlanned · supply quality
12 customers affected · began Wed 12 Aug, 10:06 · scheduled until 17:00 (6 h 54 min)
NaasFault
479 customers affected · began Wed 12 Aug, 09:25 · restored 10:47 (1 h 22 min) · 17 min later than ESB estimated
DunfirthPlanned · supply quality
13 customers affected · began Tue 11 Aug, 12:14 · scheduled until 17:00 (4 h 46 min)
AthyPlanned · supply quality
109 customers affected · began Tue 11 Aug, 10:42 · listed for about 4 h 30 min · no end time published
SallinsPlanned · network upgrade
42 customers affected · began Tue 11 Aug, 10:09 · listed for about 4 h 30 min · no end time published
SallinsPlanned · supply quality
41 customers affected · began Tue 11 Aug, 09:40 · listed for about 6 h 30 min · no end time published
LeixlipFault
49 customers affected · began Tue 11 Aug, 09:13 · off for about 2 h 30 min · no restore time published
AthyPlanned
35 customers affected · began Tue 11 Aug, 09:10 · scheduled until 17:00 (7 h 50 min)
DunfirthPlanned · supply quality
47 customers affected · began Mon 10 Aug, 11:01 · listed for about 5 h · no end time published
JohnstownFault
402 customers affected · began Mon 10 Aug, 10:27 · restored 11:52 (1 h 25 min) · 22 min later than ESB estimated
SallinsPlanned · supply quality
23 customers affected · began Mon 10 Aug, 10:14 · scheduled until 17:00 (6 h 46 min)
KilcullenFault
13 customers affected · began Mon 10 Aug, 09:38 · restored 12:24 (2 h 46 min) · 1 h 6 min earlier than ESB estimated
SallinsFault
182 customers affected · began Mon 10 Aug, 09:23 · restored 17:14 (7 h 51 min) · 14 min later than ESB estimated
SallinsFault
361 customers affected · began Sat 8 Aug, 14:24 · restored 14:57 (33 min) · 33 min earlier than ESB estimated
NaasFault
1,275 customers affected · began Sat 8 Aug, 06:16 · restored 06:33 (17 min) · 57 min earlier than ESB estimated
AthyFault
57 customers affected · began Fri 7 Aug, 15:26 · restored 16:26 (1 h) · 49 min earlier than ESB estimated
CelbridgeFault
14 customers affected · began Fri 7 Aug, 12:41 · expected back by 16:00 (about 3 h 30 min) · no restore time published
KilcockPlanned
65 customers affected · began Fri 7 Aug, 10:39 · listed for about 5 h 30 min · no end time published
DunfirthFault
83 customers affected · began Fri 7 Aug, 10:25 · restored 11:16 (51 min) · 44 min earlier than ESB estimated
AthyPlanned · supply quality
78 customers affected · began Fri 7 Aug, 10:15 · scheduled until 14:00 (3 h 45 min)
MonreadPlanned · network upgrade
196 customers affected · began Fri 7 Aug, 09:42 · listed for about 6 h 30 min · no end time published
AthyPlanned · supply quality
48 customers affected · began Fri 7 Aug, 09:39 · scheduled until 16:30 (6 h 51 min)
BlessingtonFault
54 customers affected · began Fri 7 Aug, 08:48 · restored 12:01 (3 h 13 min) · 1 h 1 min later than ESB estimated
MorristownFault
75 customers affected · began Thu 6 Aug, 15:31 · restored 16:50 (1 h 19 min) · 2 h 10 min earlier than ESB estimated
MoneycooleyPlanned
49 customers affected · began Thu 6 Aug, 10:51 · listed for about 4 h · no end time published
BlakePlanned · supply quality
69 customers affected · began Thu 6 Aug, 10:47 · listed for about 4 h 30 min · no end time published
BaltinglassPlanned · new connections
74 customers affected · began Thu 6 Aug, 10:31 · listed for about 4 h · no end time published
BaltinglassPlanned · supply quality
39 customers affected · began Thu 6 Aug, 09:24 · listed for about 3 h 30 min · no end time published
LeixlipFault
199 customers affected · began Thu 6 Aug, 09:22 · off for about 10 h · no restore time published
BlessingtonPlanned · network upgrade
32 customers affected · began Thu 6 Aug, 09:17 · scheduled until 17:00 (7 h 43 min)
BlakePlanned · new connections
72 customers affected · began Wed 5 Aug, 12:44 · listed for about 6 h · no end time published
DunfirthPlanned · supply quality
23 customers affected · began Wed 5 Aug, 11:34 · listed for about 5 h · no end time published
KilcullenPlanned · supply quality
12 customers affected · began Wed 5 Aug, 10:13 · scheduled until 15:00 (4 h 47 min)
AthyPlanned · supply quality
198 customers affected · began Wed 5 Aug, 09:12 · scheduled until 16:30 (7 h 18 min)
KildarePlanned · supply quality
10 customers affected · began Tue 4 Aug, 12:09 · scheduled until 17:00 (4 h 51 min)
MorristownFault
79 customers affected · began Tue 4 Aug, 10:53 · restored 16:05 (5 h 12 min) · 2 h 35 min later than ESB estimated
JohnstownPlanned · supply quality
29 customers affected · began Tue 4 Aug, 10:00 · listed for about 5 h · no end time published
BlessingtonPlanned · network upgrade
36 customers affected · began Tue 4 Aug, 09:56 · listed for about 4 h · no end time published
BlessingtonPlanned · network upgrade
11 customers affected · began Tue 4 Aug, 09:55 · listed for about 5 h · no end time published
AthyFault
16 customers affected · began Tue 4 Aug, 08:53 · restored 10:30 (1 h 37 min) · 15 min earlier than ESB estimated
KilcockFault
431 customers affected · began Sun 2 Aug, 03:13 · restored 04:03 (50 min) · 12 min earlier than ESB estimated
KilcullenFault
10 customers affected · began Sat 1 Aug, 09:47 · restored 11:49 (2 h 2 min) · 1 h 56 min earlier than ESB estimated