Too few faults in November 2026 to grade fairly.
Outage history · 273 outages
This list as a CSV file, one row per outage, times in UTC.
GraiguenamanaghPlanned
29 customers affected · began Wed 11 Nov, 09:39 · scheduled until 18:00 (8 h 21 min) · still listed when last checked
CastlecomerFault
268 customers affected · began Wed 11 Nov, 09:15 · still out when last checked · expected back by 13:00
- Outage began · 51 customers
- 268 customers still off
- Last seen still out
McdonaghPlanned · new connections
83 customers affected · began Tue 10 Nov, 10:33 · listed for about 5 h · no end time published
GraiguenamanaghPlanned · network upgrade
55 customers affected · began Tue 10 Nov, 10:20 · listed for about 5 h · no end time published
GraiguenamanaghPlanned · network upgrade
214 customers affected · began Mon 9 Nov, 10:51 · scheduled until 16:30 (5 h 39 min)
CastlecomerPlanned · new connections
35 customers affected · began Mon 9 Nov, 10:32 · listed for about 4 h 30 min · no end time published
BallyhalePlanned · new connections
43 customers affected · began Mon 9 Nov, 10:03 · listed for about 4 h 30 min · no end time published
Talbots InchFault
11 customers affected · began Fri 6 Nov, 15:41 · restored 17:05 (1 h 24 min) · 1 h 40 min earlier than ESB estimated
- Outage began · 10 customers
- 11 customers still off
- Supply restored
BallyhalePlanned · line diversion
20 customers affected · began Fri 6 Nov, 10:17 · scheduled until 16:00 (5 h 43 min)
GoresbridgePlanned
70 customers affected · began Fri 6 Nov, 09:36 · scheduled until 18:00 (8 h 24 min)
RosehillFault
1,405 customers affected · began Thu 5 Nov, 19:39 · restored 20:48 (1 h 9 min)
Mount MiseryPlanned · supply quality
151 customers affected · began Thu 5 Nov, 09:43 · listed for about 7 h · no end time published
Mount MiseryPlanned · supply quality
113 customers affected · began Thu 5 Nov, 09:11 · listed for about 5 h · no end time published
BallyraggetFault
38 customers affected · began Wed 4 Nov, 16:36 · restored 18:40 (2 h 4 min)
CastlecomerPlanned · new connections
35 customers affected · began Wed 4 Nov, 10:08 · listed for about 5 h 30 min · no end time published
GraiguenamanaghPlanned · network upgrade
40 customers affected · began Wed 4 Nov, 10:07 · scheduled until 16:30 (6 h 23 min)
CastlecomerPlanned
57 customers affected · began Wed 4 Nov, 09:58 · listed for about 6 h · no end time published
BallyhalePlanned · network upgrade
148 customers affected · began Wed 4 Nov, 09:27 · scheduled until 17:00 (7 h 33 min)
McdonaghPlanned · supply quality
13 customers affected · began Tue 3 Nov, 11:05 · listed for about 3 h 30 min · no end time published
Talbots InchPlanned
43 customers affected · began Tue 3 Nov, 11:00 · listed for about 4 h 30 min · no end time published
BallyhalePlanned · line diversion
117 customers affected · began Tue 3 Nov, 10:20 · scheduled until 17:30 (7 h 10 min)
BallyhalePlanned · network upgrade
58 customers affected · began Mon 2 Nov, 11:01 · scheduled until 16:30 (5 h 29 min)
BallyhalePlanned · network upgrade
41 customers affected · began Mon 2 Nov, 10:37 · scheduled until 16:30 (5 h 53 min)
BallyraggetPlanned · new connections
36 customers affected · began Mon 2 Nov, 10:34 · listed for about 4 h 30 min · no end time published
McdonaghPlanned · network upgrade
31 customers affected · began Mon 2 Nov, 09:44 · listed for about 4 h 30 min · no end time published
RosberconFault
603 customers affected · began Fri 30 Oct, 16:34 · restored 16:57 (23 min) · 48 min earlier than ESB estimated
GranaghPlanned · supply quality
218 customers affected · began Fri 30 Oct, 09:55 · listed for about 4 h 30 min · no end time published
CastlecomerPlanned
58 customers affected · began Thu 29 Oct, 13:43 · scheduled until 17:00 (3 h 17 min)
BallyhaleFault
18 customers affected · began Thu 29 Oct, 11:29 · off for about 1 h · no restore time published
RosberconPlanned · network upgrade
184 customers affected · began Thu 29 Oct, 10:03 · listed for about 3 h 30 min · no end time published
BallyraggetFault
96 customers affected · began Thu 29 Oct, 09:15 · off for about 1 h · no restore time published
BallyraggetPlanned · supply quality
467 customers affected · began Thu 29 Oct, 09:01 · listed for about 5 h 30 min · no end time published
RosberconPlanned · supply quality
12 customers affected · began Wed 28 Oct, 13:46 · listed for about 1 h 30 min · no end time published
RosehillPlanned · supply quality
106 customers affected · began Wed 28 Oct, 13:26 · listed for about 2 h · no end time published
RosehillPlanned · supply quality
15 customers affected · began Wed 28 Oct, 11:08 · listed for about 4 h 30 min · no end time published
BallyraggetPlanned · new connections
96 customers affected · began Wed 28 Oct, 11:03 · scheduled until 14:00 (2 h 57 min)
CastlecomerPlanned
33 customers affected · began Wed 28 Oct, 11:03 · listed for about 6 h · no end time published
CallanPlanned · new connections
46 customers affected · began Wed 28 Oct, 10:37 · listed for about 3 h · no end time published
BallyraggetPlanned
38 customers affected · began Wed 28 Oct, 09:26 · listed for about 5 h · no end time published
McdonaghPlanned · supply quality
94 customers affected · began Wed 28 Oct, 09:22 · scheduled until 17:00 (7 h 38 min)
CallanFault
76 customers affected · began Tue 27 Oct, 18:04 · restored 19:57 (1 h 53 min) · 1 h 3 min earlier than ESB estimated
CastlecomerPlanned
64 customers affected · began Tue 27 Oct, 11:54 · listed for about 4 h · no end time published
GraiguenamanaghPlanned · supply quality
35 customers affected · began Tue 27 Oct, 10:55 · scheduled until 17:00 (6 h 5 min)
RosberconPlanned · network upgrade
111 customers affected · began Tue 27 Oct, 09:54 · listed for about 4 h 30 min · no end time published
BallyhaleFault
19 customers affected · began Mon 26 Oct, 20:58 · restored 23:04 (2 h 6 min) · 26 min earlier than ESB estimated
BallyhaleFault
71 customers affected · began Mon 26 Oct, 20:17 · restored 23:58 (3 h 41 min) · 47 min earlier than ESB estimated
BallyhaleFault
37 customers affected · began Mon 26 Oct, 19:07 · restored 20:45 (1 h 38 min) · 1 h 30 min earlier than ESB estimated
BallyhaleFault
25 customers affected · began Mon 26 Oct, 18:24 · restored 19:07 (43 min) · 1 h 23 min earlier than ESB estimated
GranaghFault
227 customers affected · began Sun 25 Oct, 07:15 · restored 15:30 (8 h 15 min) · 2 h 30 min earlier than ESB estimated
CastlecomerFault
1,437 customers affected · began Sun 25 Oct, 00:23 · expected back by 01:30 (about 1 h) · no restore time published
GranaghFault
227 customers affected · began Sat 24 Oct, 21:41 · restored Sun 25 Oct, 01:24 (3 h 43 min) · 39 min later than ESB estimated
GranaghFault
414 customers affected · began Sat 24 Oct, 21:34 · restored 21:38 (4 min) · 1 h 7 min earlier than ESB estimated
GranaghFault
868 customers affected · began Sat 24 Oct, 21:33 · restored 21:41 (8 min) · 1 h 4 min earlier than ESB estimated
GranaghFault
1,479 customers affected · began Sat 24 Oct, 20:56 · restored 21:32 (36 min) · 17 h 28 min earlier than ESB estimated
- Outage began · 1,479 customers
- 1,065 customers still off
- Supply restored
GranaghFault
1,065 customers affected · began Sat 24 Oct, 20:25 · restored 21:39 (1 h 14 min) · 9 min later than ESB estimated
- Outage began · 1,065 customers
- 673 customers still off
- Supply restored
Cregg RoadFault
23 customers affected · began Fri 23 Oct, 11:09 · restored 16:05 (4 h 56 min) · 1 h 55 min earlier than ESB estimated
GraiguenamanaghPlanned · network upgrade
59 customers affected · began Fri 23 Oct, 08:10 · listed for about 8 h 30 min · no end time published
BallyraggetPlanned · supply quality
36 customers affected · began Thu 22 Oct, 10:34 · listed for about 2 h 30 min · no end time published
GoresbridgePlanned
16 customers affected · began Thu 22 Oct, 09:58 · listed for about 6 h · no end time published
BagenalstownPlanned · new connections
65 customers affected · began Thu 22 Oct, 09:54 · listed for about 4 h 30 min · no end time published
CastlecomerPlanned · supply quality
38 customers affected · began Wed 21 Oct, 10:54 · listed for about 5 h · no end time published
BallyraggetPlanned · new connections
13 customers affected · began Wed 21 Oct, 10:42 · scheduled until 16:00 (5 h 18 min)
McdonaghPlanned · new connections
23 customers affected · began Tue 20 Oct, 10:22 · listed for about 3 h · no end time published
CastlecomerPlanned · supply quality
34 customers affected · began Mon 19 Oct, 11:45 · listed for about 5 h · no end time published
RosberconPlanned · network upgrade
111 customers affected · began Mon 19 Oct, 10:34 · listed for about 5 h 30 min · no end time published
BallyhalePlanned · new connections
48 customers affected · began Mon 19 Oct, 10:23 · listed for about 5 h · no end time published
RosberconPlanned · supply quality
162 customers affected · began Mon 19 Oct, 10:17 · listed for about 5 h 30 min · no end time published
CastlecomerPlanned · line diversion
242 customers affected · began Fri 16 Oct, 10:19 · listed for about 4 h · no end time published
Talbots InchPlanned · network upgrade
231 customers affected · began Fri 16 Oct, 10:07 · listed for about 6 h · no end time published
CallanPlanned · supply quality
23 customers affected · began Fri 16 Oct, 09:45 · scheduled until 13:30 (3 h 45 min)
UrlingfordFault
58 customers affected · began Thu 15 Oct, 12:44 · restored 19:41 (6 h 57 min) · 1 h 19 min earlier than ESB estimated
Talbots InchFault
11 customers affected · began Thu 15 Oct, 11:16 · restored 16:42 (5 h 26 min)
CallanPlanned · supply quality
61 customers affected · began Thu 15 Oct, 10:30 · listed for about 3 h 30 min · no end time published
DeerparkFault
22 customers affected · began Wed 14 Oct, 15:13 · restored 16:48 (1 h 35 min) · 2 h 27 min earlier than ESB estimated
McdonaghPlanned
66 customers affected · began Wed 14 Oct, 10:25 · listed for about 5 h · no end time published
Cregg RoadPlanned · supply quality
141 customers affected · began Wed 14 Oct, 09:59 · listed for about 3 h 30 min · no end time published
RosberconFault
12 customers affected · began Tue 13 Oct, 17:45 · restored 20:48 (3 h 3 min) · 1 h 12 min earlier than ESB estimated
CastlecomerPlanned · supply quality
42 customers affected · began Tue 13 Oct, 10:16 · scheduled until 17:00 (6 h 44 min)
GranaghPlanned · line diversion
65 customers affected · began Tue 13 Oct, 10:05 · scheduled until 16:00 (5 h 55 min)
BallyhaleFault
43 customers affected · began Tue 13 Oct, 07:56 · restored 09:27 (1 h 31 min) · 18 min earlier than ESB estimated
CallanPlanned · new connections
66 customers affected · began Mon 12 Oct, 10:19 · scheduled until 16:00 (5 h 41 min)
RosehillPlanned · network upgrade
264 customers affected · began Mon 12 Oct, 09:51 · listed for about 6 h · no end time published
CallanPlanned · supply quality
13 customers affected · began Fri 9 Oct, 09:54 · listed for about 5 h · no end time published
CastlecomerPlanned · network upgrade
45 customers affected · began Fri 9 Oct, 09:27 · listed for about 3 h 30 min · no end time published
GraiguenamanaghFault
10 customers affected · began Thu 8 Oct, 21:45 · off for about 30 min · no restore time published
GraiguenamanaghFault
16 customers affected · began Thu 8 Oct, 21:39 · off for about 30 min · no restore time published
GraiguenamanaghFault
448 customers affected · began Thu 8 Oct, 21:32 · restored 23:37 (2 h 5 min) · 22 min later than ESB estimated
- Outage began · 238 customers
- 448 customers still off
- Supply restored
BallyhalePlanned · new connections
14 customers affected · began Thu 8 Oct, 10:47 · scheduled until 16:00 (5 h 13 min)
Purcells InchPlanned · supply quality
20 customers affected · began Thu 8 Oct, 10:02 · listed for about 3 h · no end time published
CallanPlanned · supply quality
19 customers affected · began Thu 8 Oct, 09:43 · listed for about 4 h · no end time published
BallyhalePlanned · new connections
1,137 customers affected · began Thu 8 Oct, 09:17 · listed for about 1 h · no end time published
BagenalstownPlanned · new connections
41 customers affected · began Wed 7 Oct, 10:14 · scheduled until 16:00 (5 h 46 min)
RosberconPlanned · supply quality
236 customers affected · began Wed 7 Oct, 09:34 · listed for about 2 h 30 min · no end time published
BagenalstownPlanned · supply quality
13 customers affected · began Tue 6 Oct, 10:39 · scheduled until 17:00 (6 h 21 min)
McdonaghPlanned
89 customers affected · began Tue 6 Oct, 10:24 · listed for about 5 h 30 min · no end time published
CallanFault
1,427 customers affected · began Tue 6 Oct, 09:51 · restored 10:08 (17 min) · 52 min earlier than ESB estimated
- Outage began · 1,427 customers
- 621 customers still off
- Supply restored
CastlecomerPlanned · network upgrade
41 customers affected · began Tue 6 Oct, 09:50 · scheduled until 17:00 (7 h 10 min)
CallanFault
3,641 customers affected · began Tue 6 Oct, 09:08 · off for about 30 min · no restore time published
BallyhalePlanned · network upgrade
20 customers affected · began Mon 5 Oct, 11:09 · scheduled until 17:00 (5 h 51 min)
BallyhalePlanned · network upgrade
45 customers affected · began Mon 5 Oct, 10:55 · listed for about 5 h 30 min · no end time published
BagenalstownPlanned · supply quality
41 customers affected · began Mon 5 Oct, 10:46 · scheduled until 17:00 (6 h 14 min)
BallyhalePlanned · network upgrade
38 customers affected · began Mon 5 Oct, 09:18 · listed for about 1 h 30 min · no end time published
Purcells InchPlanned · supply quality
35 customers affected · began Fri 2 Oct, 10:17 · listed for about 4 h · no end time published
McdonaghPlanned
16 customers affected · began Fri 2 Oct, 09:59 · scheduled until Tue 6 Oct, 17:00 (4 days)
RosberconPlanned · line diversion
106 customers affected · began Thu 1 Oct, 10:31 · scheduled until 16:00 (5 h 29 min)
GraiguenamanaghPlanned · supply quality
45 customers affected · began Thu 1 Oct, 10:21 · scheduled until 17:00 (6 h 39 min)
RosehillFault
20 customers affected · began Wed 30 Sep, 15:04 · restored 16:51 (1 h 47 min) · 9 min earlier than ESB estimated
GranaghFault
89 customers affected · began Wed 30 Sep, 11:31 · restored 14:02 (2 h 31 min) · 2 h 58 min earlier than ESB estimated
CastlecomerFault
136 customers affected · began Wed 30 Sep, 10:48 · restored 12:47 (1 h 59 min) · 13 min earlier than ESB estimated
CastlecomerFault
15 customers affected · began Wed 30 Sep, 09:43 · restored 12:38 (2 h 55 min) · 1 h 22 min earlier than ESB estimated
BallyhaleFault
79 customers affected · began Wed 30 Sep, 09:06 · restored 10:57 (1 h 51 min)
BagenalstownFault
140 customers affected · began Tue 29 Sep, 22:09 · restored 23:53 (1 h 44 min) · 16 h 7 min earlier than ESB estimated
- Outage began · 77 customers
- 140 customers still off
- Supply restored
BallyhaleFault
13 customers affected · began Tue 29 Sep, 21:12 · restored 21:57 (45 min)
CastlecomerFault
136 customers affected · began Tue 29 Sep, 21:02 · restored Wed 30 Sep, 10:38 (13 h 36 min) · 3 h 22 min earlier than ESB estimated
McdonaghFault
137 customers affected · began Tue 29 Sep, 20:56 · off for about 3 h · no restore time published
BallyraggetFault
1,741 customers affected · began Tue 29 Sep, 20:22 · restored 22:18 (1 h 56 min) · 17 h 42 min earlier than ESB estimated
BallyhaleFault
1,136 customers affected · began Tue 29 Sep, 20:21 · restored Wed 30 Sep, 00:02 (3 h 41 min) · 17 h 58 min earlier than ESB estimated
- Outage began · 1,136 customers
4 further updates
- 487 customers still off
- 473 customers still off
- 470 customers still off
- 237 customers still off
- Supply restored
BagenalstownFault
322 customers affected · began Tue 29 Sep, 20:06 · off for about 3 h · no restore time published
- Outage began · 322 customers
2 further updates
- 140 customers still off
- 63 customers still off
- Last seen still out
GranaghFault
255 customers affected · began Tue 29 Sep, 20:06 · restored 22:29 (2 h 23 min) · 1 h 31 min earlier than ESB estimated
McdonaghFault
398 customers affected · began Tue 29 Sep, 19:57 · restored Wed 30 Sep, 08:28 (12 h 31 min) · 9 h 32 min earlier than ESB estimated
- Outage began · 398 customers
- 173 customers still off
- Supply restored
McdonaghFault
683 customers affected · began Tue 29 Sep, 19:16 · restored Wed 30 Sep, 08:29 (13 h 13 min) · 7 h 31 min earlier than ESB estimated
- Outage began · 683 customers
- 285 customers still off
- Supply restored
BagenalstownFault
761 customers affected · began Tue 29 Sep, 18:59 · restored Wed 30 Sep, 00:14 (5 h 15 min) · 15 h 46 min earlier than ESB estimated
- Outage began · 761 customers
- 95 customers still off
- Supply restored
McdonaghFault
683 customers affected · began Tue 29 Sep, 18:56 · off for about 1 h · no restore time published
Repeat fault - outage 2 of 2 at this location in quick succession
- Outage began · 683 customers
- 414 customers still off
- Last seen still out
BagenalstownFault
35 customers affected · began Tue 29 Sep, 18:39 · restored Wed 30 Sep, 01:36 (6 h 57 min) · 14 h 24 min earlier than ESB estimated
BagenalstownFault
83 customers affected · began Tue 29 Sep, 18:36 · restored Wed 30 Sep, 01:35 (6 h 59 min) · 14 h 25 min earlier than ESB estimated
Purcells InchFault
45 customers affected · began Tue 29 Sep, 18:02 · expected back by 21:00 (about 3 h) · no restore time published
McdonaghFault
1,097 customers affected · began Tue 29 Sep, 17:33 · restored 18:55 (1 h 22 min)
Repeat fault - outage 1 of 2 at this location in quick succession
- Outage began · 1,097 customers
- 414 customers still off
- Supply restored
UrlingfordFault
672 customers affected · began Tue 29 Sep, 12:42 · restored 16:43 (4 h 1 min) · 47 min earlier than ESB estimated
BagenalstownPlanned
439 customers affected · began Tue 29 Sep, 09:20 · listed for about 8 h 30 min · no end time published
- Outage began · 439 customers
- 374 customers still off
- Last listed
RosehillPlanned · new connections
51 customers affected · began Mon 28 Sep, 11:02 · scheduled until 16:00 (4 h 58 min)
GranaghFault
673 customers affected · began Sat 26 Sep, 09:13 · restored 09:30 (17 min) · 45 min earlier than ESB estimated
Talbots InchPlanned · supply quality
23 customers affected · began Fri 25 Sep, 14:48 · listed for about 2 h · no end time published
CallanPlanned
169 customers affected · began Thu 24 Sep, 10:55 · listed for about 5 h · no end time published
GranaghPlanned · line diversion
57 customers affected · began Thu 24 Sep, 10:33 · listed for about 5 h · no end time published
Purcells InchPlanned · supply quality
24 customers affected · began Wed 23 Sep, 10:51 · listed for about 5 h 30 min · no end time published
BallyraggetPlanned · new connections
30 customers affected · began Wed 23 Sep, 10:16 · listed for about 4 h · no end time published
BallyhalePlanned · new connections
32 customers affected · began Wed 23 Sep, 10:03 · listed for about 4 h 30 min · no end time published
Purcells InchFault
56 customers affected · began Tue 22 Sep, 19:50 · restored 21:00 (1 h 10 min) · 1 h earlier than ESB estimated
Mount MiseryPlanned · network upgrade
58 customers affected · began Tue 22 Sep, 11:18 · listed for about 4 h · no end time published
BallyhalePlanned · new connections
124 customers affected · began Tue 22 Sep, 10:30 · listed for about 4 h · no end time published
BallyhalePlanned · network upgrade
172 customers affected · began Tue 22 Sep, 09:08 · listed for about 7 h 30 min · no end time published
CastlecomerPlanned · network upgrade
32 customers affected · began Mon 21 Sep, 10:48 · scheduled until 17:00 (6 h 12 min)
CastlecomerPlanned · new connections
40 customers affected · began Mon 21 Sep, 10:33 · scheduled until 16:00 (5 h 27 min)
CastlecomerPlanned · supply quality
70 customers affected · began Mon 21 Sep, 10:15 · scheduled until 17:00 (6 h 45 min)
BallyraggetPlanned · network upgrade
28 customers affected · began Mon 21 Sep, 10:13 · listed for about 4 h 30 min · no end time published
DeerparkFault
22 customers affected · began Mon 21 Sep, 07:43 · restored 09:57 (2 h 14 min) · 1 h 33 min earlier than ESB estimated
Cregg RoadFault
31 customers affected · began Mon 21 Sep, 07:20 · restored 11:57 (4 h 37 min)
RosehillPlanned · network upgrade
17 customers affected · began Fri 18 Sep, 10:22 · scheduled until 17:00 (6 h 38 min)
Purcells InchPlanned · new connections
10 customers affected · began Fri 18 Sep, 10:17 · scheduled until 16:00 (5 h 43 min)
CastlecomerPlanned · supply quality
42 customers affected · began Fri 18 Sep, 09:53 · listed for about 6 h · no end time published
RosehillPlanned · network upgrade
321 customers affected · began Fri 18 Sep, 09:33 · scheduled until 17:00 (7 h 27 min)
RosehillPlanned
54 customers affected · began Thu 17 Sep, 10:40 · listed for about 6 h · no end time published
CastlecomerPlanned · supply quality
70 customers affected · began Thu 17 Sep, 10:06 · scheduled until 17:00 (6 h 54 min)
Mount MiseryFault
10 customers affected · began Thu 17 Sep, 07:51 · restored 08:54 (1 h 3 min) · 36 min earlier than ESB estimated
UrlingfordPlanned · network upgrade
18 customers affected · began Wed 16 Sep, 13:44 · listed for about 3 h · no end time published
CastlecomerPlanned · supply quality
35 customers affected · began Wed 16 Sep, 12:01 · listed for about 4 h · no end time published
BallyraggetPlanned · new connections
59 customers affected · began Wed 16 Sep, 10:26 · scheduled until 16:00 (5 h 34 min)
Talbots InchPlanned · new connections
27 customers affected · began Wed 16 Sep, 10:20 · scheduled until 17:00 (6 h 40 min)
McdonaghPlanned
17 customers affected · began Tue 15 Sep, 10:19 · listed for about 6 h 30 min · no end time published
McdonaghPlanned · line diversion
39 customers affected · began Tue 15 Sep, 10:14 · listed for about 3 h 30 min · no end time published
CastlecomerPlanned · network upgrade
240 customers affected · began Tue 15 Sep, 09:53 · scheduled until 17:00 (7 h 7 min)
GraiguenamanaghPlanned · supply quality
73 customers affected · began Mon 14 Sep, 11:19 · scheduled until 17:00 (5 h 41 min)
GraiguenamanaghPlanned · line diversion
55 customers affected · began Mon 14 Sep, 10:39 · listed for about 1 h 30 min · no end time published
GraiguenamanaghPlanned · new connections
60 customers affected · began Mon 14 Sep, 10:13 · scheduled until 16:00 (5 h 47 min)
CallanFault
13 customers affected · began Sat 12 Sep, 09:18 · restored 10:18 (1 h) · 1 h 12 min earlier than ESB estimated
GraiguenamanaghPlanned · network upgrade
70 customers affected · began Fri 11 Sep, 09:52 · listed for about 5 h 30 min · no end time published
RosberconPlanned · supply quality
236 customers affected · began Fri 11 Sep, 09:24 · listed for about 5 h · no end time published
BallyhalePlanned · supply quality
52 customers affected · began Fri 11 Sep, 09:11 · listed for about 4 h 30 min · no end time published
BagenalstownPlanned · supply quality
52 customers affected · began Thu 10 Sep, 10:42 · listed for about 5 h 30 min · no end time published
GranaghPlanned · new connections
14 customers affected · began Thu 10 Sep, 09:52 · listed for about 30 min · no end time published
Cregg RoadPlanned · line diversion
16 customers affected · began Wed 9 Sep, 10:20 · scheduled until 16:00 (5 h 40 min)
CastlecomerFault
51 customers affected · began Wed 9 Sep, 09:55 · restored 12:51 (2 h 56 min) · 54 min earlier than ESB estimated
- Outage began · 51 customers
- 11 customers still off
- Supply restored
GraiguenamanaghPlanned · network upgrade
30 customers affected · began Wed 9 Sep, 09:45 · listed for about 5 h 30 min · no end time published
RosberconFault
15 customers affected · began Tue 8 Sep, 10:53 · expected back by 12:30 (about 1 h 30 min) · no restore time published
BallyhaleFault
25 customers affected · began Mon 7 Sep, 14:08 · restored 16:20 (2 h 12 min) · 10 min earlier than ESB estimated
Talbots InchPlanned · new connections
68 customers affected · began Mon 7 Sep, 11:19 · listed for about 4 h · no end time published
GraiguenamanaghPlanned · network upgrade
99 customers affected · began Mon 7 Sep, 11:08 · listed for about 3 h 30 min · no end time published
GraiguenamanaghPlanned · network upgrade
58 customers affected · began Mon 7 Sep, 09:39 · listed for about 4 h · no end time published
BallyhaleFault
28 customers affected · began Sat 5 Sep, 12:10 · restored 14:39 (2 h 29 min) · 1 h 21 min earlier than ESB estimated
Purcells InchPlanned · new connections
26 customers affected · began Fri 4 Sep, 09:45 · listed for about 3 h · no end time published
Talbots InchPlanned · network upgrade
65 customers affected · began Fri 4 Sep, 09:30 · listed for about 6 h 30 min · no end time published
BallyhalePlanned · supply quality
194 customers affected · began Fri 4 Sep, 08:59 · listed for about 5 h · no end time published
RosberconFault
26 customers affected · began Thu 3 Sep, 20:19 · restored Fri 4 Sep, 01:30 (5 h 11 min) · 4 h 30 min earlier than ESB estimated
RosberconFault
26 customers affected · began Thu 3 Sep, 17:59 · restored 19:10 (1 h 11 min) · 50 min earlier than ESB estimated
CallanFault
12 customers affected · began Thu 3 Sep, 13:11 · restored 15:02 (1 h 51 min) · 1 h 58 min earlier than ESB estimated
McdonaghPlanned
32 customers affected · began Thu 3 Sep, 11:14 · listed for about 3 h 30 min · no end time published
CallanPlanned · new connections
43 customers affected · began Thu 3 Sep, 10:04 · listed for about 4 h 30 min · no end time published
CallanPlanned · supply quality
66 customers affected · began Thu 3 Sep, 10:02 · listed for about 6 h · no end time published
CastlecomerPlanned · network upgrade
44 customers affected · began Thu 3 Sep, 10:01 · listed for about 5 h · no end time published
- Outage began · 44 customers
- 33 customers still off
- Last listed
GraiguenamanaghFault
10 customers affected · began Wed 2 Sep, 15:51 · restored 18:42 (2 h 51 min) · 2 h 18 min earlier than ESB estimated
GoresbridgePlanned · supply quality
23 customers affected · began Wed 2 Sep, 11:18 · scheduled until 17:00 (5 h 42 min)
McdonaghPlanned
70 customers affected · began Wed 2 Sep, 10:30 · listed for about 5 h · no end time published
RosberconPlanned · new connections
34 customers affected · began Wed 2 Sep, 10:15 · scheduled until 16:00 (5 h 45 min)
Talbots InchPlanned
43 customers affected · began Tue 1 Sep, 13:25 · listed for about 1 h · no end time published
Talbots InchPlanned
72 customers affected · began Mon 31 Aug, 10:57 · listed for about 5 h 30 min · no end time published
BallyhalePlanned · network upgrade
112 customers affected · began Mon 31 Aug, 09:54 · scheduled until 17:00 (7 h 6 min)
GraiguenamanaghFault
51 customers affected · began Sun 30 Aug, 16:44 · restored 17:31 (47 min) · 14 min earlier than ESB estimated
GraiguenamanaghFault
25 customers affected · began Sun 30 Aug, 12:30 · restored 14:15 (1 h 45 min) · 1 h earlier than ESB estimated
GraiguenamanaghFault
51 customers affected · began Sun 30 Aug, 12:28 · restored 14:15 (1 h 47 min) · 1 h 15 min earlier than ESB estimated
McdonaghFault
1,512 customers affected · began Sat 29 Aug, 09:44 · restored 10:47 (1 h 3 min)
Talbots InchFault
119 customers affected · began Sat 29 Aug, 09:44 · restored 11:06 (1 h 22 min) · 2 h 9 min earlier than ESB estimated
BallyraggetPlanned · network upgrade
59 customers affected · began Fri 28 Aug, 12:19 · scheduled until 19:00 (6 h 41 min)
Mount MiseryFault
17 customers affected · began Fri 28 Aug, 12:01 · restored 13:21 (1 h 20 min) · 1 h 39 min earlier than ESB estimated
BallyraggetPlanned · new connections
17 customers affected · began Fri 28 Aug, 10:36 · scheduled until 16:00 (5 h 24 min)
RosehillFault
560 customers affected · began Fri 28 Aug, 07:24 · restored 07:45 (21 min) · 45 min earlier than ESB estimated
Mount MiseryFault
18 customers affected · began Thu 27 Aug, 19:52 · off for about 15 h · no restore time published
CallanPlanned
51 customers affected · began Thu 27 Aug, 14:50 · listed for about 1 h 30 min · no end time published
CallanPlanned · new connections
81 customers affected · began Thu 27 Aug, 09:59 · scheduled until 16:00 (6 h 1 min)
Talbots InchPlanned · network upgrade
32 customers affected · began Thu 27 Aug, 09:31 · listed for about 5 h 30 min · no end time published
CallanFault
353 customers affected · began Thu 27 Aug, 07:31 · off for about 4 h 30 min · no restore time published
- Outage began · 353 customers
- 51 customers still off
- Last seen still out
RosehillPlanned · new connections
20 customers affected · began Wed 26 Aug, 10:21 · listed for about 5 h · no end time published
CallanPlanned · supply quality
71 customers affected · began Wed 26 Aug, 09:54 · listed for about 4 h · no end time published
GranaghPlanned · supply quality
64 customers affected · began Wed 26 Aug, 09:42 · listed for about 5 h 30 min · no end time published
BagenalstownPlanned · supply quality
41 customers affected · began Tue 25 Aug, 09:50 · listed for about 4 h 30 min · no end time published
RosberconFault
232 customers affected · began Mon 24 Aug, 07:44 · restored 21:53 (14 h 9 min) · 7 min earlier than ESB estimated
- Outage began · 232 customers
- 11 customers still off
- Supply restored
CallanPlanned
40 customers affected · began Fri 21 Aug, 12:59 · listed for about 3 h · no end time published
RosberconFault
162 customers affected · began Fri 21 Aug, 09:22 · off for about 4 h · no restore time published
Mount MiseryPlanned · supply quality
151 customers affected · began Fri 21 Aug, 09:06 · listed for about 2 h 30 min · no end time published
BallyraggetFault
96 customers affected · began Thu 20 Aug, 17:55 · restored 19:45 (1 h 50 min) · 2 h 15 min earlier than ESB estimated
BallyhalePlanned · new connections
13 customers affected · began Thu 20 Aug, 10:21 · listed for about 4 h · no end time published
BallyraggetPlanned · supply quality
31 customers affected · began Thu 20 Aug, 09:59 · listed for about 4 h · no end time published
GraiguenamanaghPlanned · new connections
70 customers affected · began Thu 20 Aug, 09:51 · listed for about 4 h 30 min · no end time published
GranaghPlanned · supply quality
254 customers affected · began Thu 20 Aug, 09:33 · listed for about 5 h · no end time published
BallyhaleFault
1,118 customers affected · began Wed 19 Aug, 15:51 · restored 16:28 (37 min) · 32 min earlier than ESB estimated
Cregg RoadPlanned · new connections
27 customers affected · began Wed 19 Aug, 13:39 · scheduled until 17:00 (3 h 21 min)
Talbots InchFault
148 customers affected · began Wed 19 Aug, 13:23 · off for about 1 h 30 min · no restore time published
Talbots InchPlanned · new connections
110 customers affected · began Wed 19 Aug, 11:07 · listed for about 6 h · no end time published
Talbots InchPlanned
65 customers affected · began Wed 19 Aug, 10:38 · listed for about 5 h · no end time published
BallyraggetPlanned · supply quality
154 customers affected · began Wed 19 Aug, 10:35 · scheduled until 17:00 (6 h 25 min)
RosehillFault
129 customers affected · began Wed 19 Aug, 10:02 · expected back by 12:30 (about 2 h 30 min) · no restore time published
Talbots InchFault
113 customers affected · began Wed 19 Aug, 09:59 · restored 10:30 (31 min) · 1 h 30 min earlier than ESB estimated
CastlecomerPlanned · supply quality
12 customers affected · began Wed 19 Aug, 09:52 · listed for about 6 h · no end time published
GranaghPlanned
35 customers affected · began Wed 19 Aug, 09:49 · listed for about 5 h 30 min · no end time published
GranaghPlanned
25 customers affected · began Wed 19 Aug, 09:48 · listed for about 5 h 30 min · no end time published
GoresbridgePlanned
40 customers affected · began Tue 18 Aug, 11:07 · listed for about 4 h 30 min · no end time published
CastlecomerPlanned · supply quality
26 customers affected · began Tue 18 Aug, 10:28 · scheduled until 17:00 (6 h 32 min)
GranaghPlanned · network upgrade
14 customers affected · began Mon 17 Aug, 12:46 · listed for about 1 h · no end time published
McdonaghPlanned
20 customers affected · began Mon 17 Aug, 12:06 · scheduled until 17:30 (5 h 24 min)
CastlecomerPlanned
134 customers affected · began Mon 17 Aug, 11:01 · listed for about 5 h 30 min · no end time published
Cregg RoadPlanned
178 customers affected · began Mon 17 Aug, 09:45 · scheduled until 17:00 (7 h 15 min)
UrlingfordFault
17 customers affected · began Sun 16 Aug, 10:25 · restored 12:06 (1 h 41 min) · 1 h 39 min earlier than ESB estimated
BallyhaleFault
1,118 customers affected · began Sun 16 Aug, 08:26 · restored 08:41 (15 min) · 49 min earlier than ESB estimated
BagenalstownFault
20 customers affected · began Sun 16 Aug, 06:05 · restored 13:41 (7 h 36 min) · 19 min earlier than ESB estimated
- Outage began · 20 customers
- 15 customers still off
- Supply restored
RosberconPlanned · supply quality
167 customers affected · began Fri 14 Aug, 10:28 · listed for about 4 h · no end time published
CallanPlanned
16 customers affected · began Fri 14 Aug, 09:34 · scheduled until 17:00 (7 h 26 min)
RosehillPlanned · new connections
100 customers affected · began Thu 13 Aug, 10:09 · listed for about 4 h 30 min · no end time published
BallyhalePlanned · new connections
173 customers affected · began Thu 13 Aug, 09:52 · scheduled until 16:00 (6 h 8 min)
BallyhaleFault
37 customers affected · began Thu 13 Aug, 09:25 · expected back by 11:30 (about 2 h) · no restore time published
BallyhaleFault
159 customers affected · began Thu 13 Aug, 08:47 · off for about 11 h 30 min · no restore time published
- Outage began · 122 customers
2 further updates
- 40 customers still off
- 159 customers still off
- Last seen still out
McdonaghFault
1,946 customers affected · began Thu 13 Aug, 08:24 · restored 08:52 (28 min) · 3 h 8 min earlier than ESB estimated
CallanFault
40 customers affected · began Wed 12 Aug, 10:16 · expected back by 17:00 (about 6 h 30 min) · no restore time published
GranaghPlanned
161 customers affected · began Wed 12 Aug, 09:40 · scheduled until 17:00 (7 h 20 min)
RosehillPlanned · supply quality
19 customers affected · began Wed 12 Aug, 09:35 · scheduled until 17:00 (7 h 25 min)
McdonaghPlanned
258 customers affected · began Tue 11 Aug, 13:23 · listed for about 7 h · no end time published
- Outage began · 258 customers
- 24 customers still off
- Last listed
RosberconPlanned · supply quality
176 customers affected · began Tue 11 Aug, 10:40 · listed for about 6 h 30 min · no end time published
UrlingfordPlanned · line diversion
27 customers affected · began Tue 11 Aug, 10:07 · listed for about 3 h 30 min · no end time published
McdonaghPlanned · supply quality
20 customers affected · began Mon 10 Aug, 15:17 · listed for about 1 h 30 min · no end time published
McdonaghPlanned · new connections
25 customers affected · began Mon 10 Aug, 10:25 · scheduled until 16:00 (5 h 35 min)
McdonaghPlanned · supply quality
119 customers affected · began Mon 10 Aug, 09:35 · scheduled until 14:00 (4 h 25 min)
McdonaghFault
282 customers affected · began Sun 9 Aug, 17:28 · off for about 22 h · no restore time published
- Outage began · 282 customers
- 23 customers still off
- Last seen still out
Cregg RoadFault
18 customers affected · began Sat 8 Aug, 09:34 · restored 14:12 (4 h 38 min) · 3 h 12 min later than ESB estimated
McdonaghFault
1,131 customers affected · began Fri 7 Aug, 13:04 · restored 13:18 (14 min) · 57 min earlier than ESB estimated
RosehillPlanned · supply quality
72 customers affected · began Fri 7 Aug, 09:53 · listed for about 4 h 30 min · no end time published
Talbots InchPlanned · new connections
68 customers affected · began Thu 6 Aug, 10:24 · scheduled until 16:00 (5 h 36 min)
Mount MiseryPlanned · supply quality
444 customers affected · began Thu 6 Aug, 09:52 · scheduled until 17:00 (7 h 8 min)
GranaghFault
38 customers affected · began Wed 5 Aug, 11:34 · restored 12:13 (39 min) · 1 h 17 min earlier than ESB estimated
CastlecomerPlanned · new connections
69 customers affected · began Wed 5 Aug, 10:08 · scheduled until 16:00 (5 h 52 min)
GranaghPlanned · supply quality
612 customers affected · began Wed 5 Aug, 09:10 · scheduled until 17:00 (7 h 50 min)
- Outage began · 612 customers
- 113 customers still off
- Scheduled end
McdonaghPlanned
13 customers affected · began Tue 4 Aug, 10:37 · listed for about 5 h · no end time published
RosberconPlanned · supply quality
78 customers affected · began Tue 4 Aug, 10:29 · scheduled until 17:00 (6 h 31 min)
UrlingfordPlanned · network upgrade
109 customers affected · began Tue 4 Aug, 09:48 · listed for about 6 h 30 min · no end time published
BallyhaleFault
1,134 customers affected · began Mon 3 Aug, 23:39 · restored Tue 4 Aug, 10:16 (10 h 37 min) · 44 min earlier than ESB estimated
- Outage began · 1,134 customers
2 further updates
- 486 customers still off
- 472 customers still off
- Supply restored
McdonaghFault
1,130 customers affected · began Sun 2 Aug, 08:23 · restored 08:54 (31 min) · 36 min earlier than ESB estimated