Outage history · 150 outages
This list as a CSV file, one row per outage, times in UTC.
AbbeyleixPlanned · new connections
41 customers affected · began Fri 25 Sep, 17:13 · scheduled until 18:00 (47 min) · still listed when last checked
AthyFault
1,443 customers affected · began Fri 25 Sep, 11:12 · restored 12:24 (1 h 12 min) · 1 h 51 min earlier than ESB estimated
AthyPlanned · line diversion
89 customers affected · began Fri 25 Sep, 10:26 · scheduled until 16:00 (5 h 34 min) · still listed when last checked
AbbeyleixPlanned · new connections
64 customers affected · began Thu 24 Sep, 10:28 · scheduled until 16:00 (5 h 32 min)
AthyPlanned · network upgrade
15 customers affected · began Thu 24 Sep, 10:01 · listed for about 4 h · no end time published
MountrathFault
163 customers affected · began Thu 24 Sep, 07:09 · restored 08:32 (1 h 23 min) · 28 min earlier than ESB estimated
CastlecomerPlanned · supply quality
57 customers affected · began Tue 22 Sep, 10:26 · scheduled until 16:00 (5 h 34 min)
MountmellickPlanned · supply quality
32 customers affected · began Tue 22 Sep, 09:49 · listed for about 6 h · no end time published
PortlaoisePlanned · new connections
117 customers affected · began Tue 22 Sep, 09:48 · listed for about 5 h 30 min · no end time published
MountrathPlanned · supply quality
42 customers affected · began Tue 22 Sep, 09:29 · scheduled until 17:00 (7 h 31 min)
PortlaoisePlanned · supply quality
17 customers affected · began Mon 21 Sep, 14:11 · listed for about 1 h 30 min · no end time published
BallyraggetPlanned · new connections
28 customers affected · began Mon 21 Sep, 10:38 · listed for about 3 h 30 min · no end time published
PortlaoisePlanned · supply quality
15 customers affected · began Mon 21 Sep, 09:48 · scheduled until 13:00 (3 h 12 min)
MountrathPlanned · supply quality
266 customers affected · began Mon 21 Sep, 09:41 · scheduled until 17:00 (7 h 19 min)
PortarlingtonFault
10 customers affected · began Sat 19 Sep, 16:16 · restored 17:41 (1 h 25 min) · 1 h 4 min earlier than ESB estimated
MountrathFault
21 customers affected · began Fri 18 Sep, 15:13 · restored 16:01 (48 min) · 59 min earlier than ESB estimated
BallyraggetPlanned · new connections
69 customers affected · began Fri 18 Sep, 11:53 · scheduled until 16:00 (4 h 7 min)
MountrathFault
28 customers affected · began Fri 18 Sep, 11:01 · restored 15:10 (4 h 9 min) · 50 min earlier than ESB estimated
PortlaoisePlanned
54 customers affected · began Fri 18 Sep, 09:41 · listed for about 6 h · no end time published
MountrathFault
28 customers affected · began Fri 18 Sep, 07:26 · restored 08:46 (1 h 20 min) · 44 min earlier than ESB estimated
MountrathPlanned · new connections
17 customers affected · began Thu 17 Sep, 11:49 · listed for about 3 h · no end time published
AbbeyleixPlanned · new connections
74 customers affected · began Thu 17 Sep, 10:11 · listed for about 8 h 30 min · no end time published
MountmellickPlanned · new connections
37 customers affected · began Thu 17 Sep, 09:49 · listed for about 5 h 30 min · no end time published
MountrathFault
28 customers affected · began Thu 17 Sep, 09:45 · restored 10:46 (1 h 1 min) · 59 min earlier than ESB estimated
MountrathPlanned · supply quality
62 customers affected · began Wed 16 Sep, 12:42 · listed for about 2 h 30 min · no end time published
PortlaoiseFault
11 customers affected · began Wed 16 Sep, 07:59 · restored 09:00 (1 h 1 min) · 1 h 45 min earlier than ESB estimated
MountrathFault
28 customers affected · began Tue 15 Sep, 19:35 · restored 22:12 (2 h 37 min) · 48 min earlier than ESB estimated
MountrathFault
85 customers affected · began Tue 15 Sep, 19:11 · restored 23:14 (4 h 3 min) · 14 min later than ESB estimated
MountrathFault
1,886 customers affected · began Tue 15 Sep, 17:49 · restored 18:18 (29 min) · 42 min earlier than ESB estimated
MountrathPlanned · supply quality
150 customers affected · began Tue 15 Sep, 09:28 · listed for about 5 h 30 min · no end time published
AbbeyleixPlanned · new connections
91 customers affected · began Mon 14 Sep, 12:43 · scheduled until 18:00 (5 h 17 min)
AbbeyleixPlanned · line diversion
15 customers affected · began Mon 14 Sep, 10:22 · listed for about 3 h · no end time published
MountrathFault
28 customers affected · began Sun 13 Sep, 05:15 · restored 07:41 (2 h 26 min) · 34 min earlier than ESB estimated
CastlecomerFault
385 customers affected · began Fri 11 Sep, 16:43 · restored 20:15 (3 h 32 min) · 45 min earlier than ESB estimated
BallyraggetPlanned · new connections
54 customers affected · began Fri 11 Sep, 10:26 · listed for about 4 h · no end time published
MountmellickPlanned · network upgrade
52 customers affected · began Fri 11 Sep, 09:50 · listed for about 2 h · no end time published
AthyFault
12 customers affected · began Thu 10 Sep, 20:33 · restored 22:22 (1 h 49 min) · 1 h 23 min earlier than ESB estimated
CastlecomerFault
35 customers affected · began Thu 10 Sep, 20:20 · off for about 30 min · no restore time published
CastlecomerFault
385 customers affected · began Thu 10 Sep, 05:15 · restored 11:23 (6 h 8 min) · 38 min later than ESB estimated
- Outage began · 385 customers
- 38 customers still off
- Supply restored
PallasFault
34 customers affected · began Wed 9 Sep, 17:08 · restored 18:10 (1 h 2 min) · 50 min earlier than ESB estimated
MountmellickPlanned · line diversion
66 customers affected · began Wed 9 Sep, 11:19 · listed for about 3 h 30 min · no end time published
PortlaoisePlanned · new connections
22 customers affected · began Wed 9 Sep, 10:49 · scheduled until 16:00 (5 h 11 min)
PortlaoisePlanned · line diversion
21 customers affected · began Wed 9 Sep, 09:15 · listed for about 2 h 30 min · no end time published
PortlaoiseFault
11 customers affected · began Tue 8 Sep, 15:54 · restored 17:43 (1 h 49 min) · 17 min earlier than ESB estimated
AthyFault
20 customers affected · began Mon 7 Sep, 21:34 · restored Tue 8 Sep, 08:57 (11 h 23 min) · 9 h 12 min later than ESB estimated
MountrathFault
36 customers affected · began Mon 7 Sep, 15:02 · restored 17:57 (2 h 55 min)
- Outage began · 33 customers
- 36 customers still off
- Supply restored
BallyraggetPlanned
156 customers affected · began Mon 7 Sep, 09:24 · scheduled until 16:30 (7 h 6 min)
MountrathFault
28 customers affected · began Sun 6 Sep, 04:09 · restored 08:46 (4 h 37 min) · 1 h 46 min later than ESB estimated
BallyraggetPlanned · new connections
116 customers affected · began Fri 4 Sep, 11:00 · scheduled until 16:00 (5 h)
AthyPlanned · network upgrade
25 customers affected · began Fri 4 Sep, 09:51 · listed for about 5 h 30 min · no end time published
CastlecomerFault
16 customers affected · began Thu 3 Sep, 18:13 · restored Fri 4 Sep, 01:24 (7 h 11 min) · 1 h 24 min later than ESB estimated
PortlaoiseFault
11 customers affected · began Thu 3 Sep, 15:57 · restored 17:24 (1 h 27 min) · 36 min earlier than ESB estimated
RathdowneyPlanned · supply quality
12 customers affected · began Thu 3 Sep, 10:04 · listed for about 5 h 30 min · no end time published
MountrathFault
28 customers affected · began Thu 3 Sep, 09:32 · restored 13:33 (4 h 1 min)
MountrathPlanned · supply quality
124 customers affected · began Thu 3 Sep, 09:20 · listed for about 6 h 30 min · no end time published
PortlaoisePlanned
80 customers affected · began Wed 2 Sep, 10:03 · scheduled until 17:00 (6 h 57 min)
PallasPlanned · network upgrade
27 customers affected · began Wed 2 Sep, 10:00 · listed for about 4 h 30 min · no end time published
AbbeyleixPlanned · line diversion
44 customers affected · began Tue 1 Sep, 16:10 · listed for about 1 h 30 min · no end time published
MountrathPlanned · supply quality
32 customers affected · began Tue 1 Sep, 15:17 · listed for about 30 min · no end time published
AthyPlanned
55 customers affected · began Tue 1 Sep, 10:18 · scheduled until 17:00 (6 h 42 min)
MountmellickPlanned · line diversion
82 customers affected · began Mon 31 Aug, 11:20 · listed for about 2 h 30 min · no end time published
AthyPlanned · network upgrade
33 customers affected · began Mon 31 Aug, 09:48 · listed for about 6 h · no end time published
GraigueFault
10 customers affected · began Sun 30 Aug, 21:19 · restored Mon 31 Aug, 13:45 (16 h 26 min) · 1 h 45 min earlier than ESB estimated
PallasFault
11 customers affected · began Sat 29 Aug, 09:03 · restored 10:47 (1 h 44 min) · 13 min earlier than ESB estimated
MountrathFault
12 customers affected · began Fri 28 Aug, 16:15 · restored 18:44 (2 h 29 min) · 29 min later than ESB estimated
RathdowneyPlanned · new connections
15 customers affected · began Fri 28 Aug, 11:22 · listed for about 2 h · no end time published
PortlaoiseFault
69 customers affected · began Fri 28 Aug, 04:51 · restored 06:52 (2 h 1 min)
PortlaoiseFault
53 customers affected · began Fri 28 Aug, 03:34 · restored 04:52 (1 h 18 min)
PortlaoiseFault
213 customers affected · began Fri 28 Aug, 01:16 · expected back by 02:30 (about 1 h) · no restore time published
PortlaoiseFault
1,583 customers affected · began Fri 28 Aug, 00:15 · expected back by 01:30 (about 1 h 30 min) · no restore time published
- Outage began · 1,583 customers
- 766 customers still off
- Estimated restore, from ESB
PortarlingtonPlanned · network upgrade
22 customers affected · began Thu 27 Aug, 14:50 · scheduled until 16:00 (1 h 10 min)
PortarlingtonPlanned · network upgrade
13 customers affected · began Thu 27 Aug, 10:08 · listed for about 2 h · no end time published
CastlecomerPlanned · new connections
64 customers affected · began Thu 27 Aug, 09:56 · listed for about 3 h · no end time published
PortlaoisePlanned · line diversion
75 customers affected · began Wed 26 Aug, 09:11 · scheduled until 16:00 (6 h 49 min)
- Outage began · 75 customers
2 further updates
- 63 customers still off
- 12 customers still off
- Scheduled end
MountrathPlanned · new connections
40 customers affected · began Tue 25 Aug, 09:57 · listed for about 3 h · no end time published
AthyPlanned · new connections
49 customers affected · began Tue 25 Aug, 09:55 · listed for about 2 h 30 min · no end time published
PortlaoisePlanned · supply quality
110 customers affected · began Tue 25 Aug, 09:36 · listed for about 7 h · no end time published
PortlaoisePlanned
16 customers affected · began Sat 22 Aug, 09:01 · listed for about 5 h · no end time published
MountrathPlanned · new connections
22 customers affected · began Fri 21 Aug, 10:57 · listed for about 1 h · no end time published
MountrathPlanned · supply quality
15 customers affected · began Fri 21 Aug, 09:58 · scheduled until 16:00 (6 h 2 min)
AthyPlanned · network upgrade
126 customers affected · began Fri 21 Aug, 09:14 · listed for about 3 h · no end time published
AthyPlanned · new connections
37 customers affected · began Thu 20 Aug, 18:28 · scheduled until 18:30 (2 min)
MountrathPlanned · supply quality
12 customers affected · began Thu 20 Aug, 10:09 · scheduled until 17:00 (6 h 51 min)
AthyPlanned · network upgrade
43 customers affected · began Thu 20 Aug, 09:23 · listed for about 5 h · no end time published
PallasPlanned · network upgrade
221 customers affected · began Wed 19 Aug, 11:16 · scheduled until 16:30 (5 h 14 min)
RathdowneyPlanned · new connections
40 customers affected · began Wed 19 Aug, 11:15 · listed for about 3 h 30 min · no end time published
RoscreaPlanned · supply quality
33 customers affected · began Wed 19 Aug, 09:58 · scheduled until 17:00 (7 h 2 min)
MountrathPlanned · supply quality
144 customers affected · began Wed 19 Aug, 09:57 · scheduled until 17:00 (7 h 3 min)
MountrathFault
39 customers affected · began Wed 19 Aug, 09:01 · off for about 1 h 30 min · no restore time published
Repeat fault - outage 2 of 2 at this location in quick succession
MountrathFault
39 customers affected · began Wed 19 Aug, 07:19 · restored 08:49 (1 h 30 min) · 56 min earlier than ESB estimated
Repeat fault - outage 1 of 2 at this location in quick succession
MountrathFault
27 customers affected · began Wed 19 Aug, 07:05 · restored 10:29 (3 h 24 min) · 1 h 31 min earlier than ESB estimated
RathdowneyFault
13 customers affected · began Wed 19 Aug, 00:12 · expected back by 07:30 (about 7 h 30 min) · no restore time published
RathdowneyFault
96 customers affected · began Wed 19 Aug, 00:03 · restored 08:11 (8 h 8 min) · 49 min earlier than ESB estimated
AbbeyleixPlanned · new connections
33 customers affected · began Tue 18 Aug, 09:47 · scheduled until 16:00 (6 h 13 min)
RathdowneyPlanned · supply quality
282 customers affected · began Tue 18 Aug, 09:40 · listed for about 7 h · no end time published
MountrathFault
24 customers affected · began Mon 17 Aug, 19:43 · restored 21:35 (1 h 52 min) · 10 min earlier than ESB estimated
BallyraggetPlanned · new connections
121 customers affected · began Mon 17 Aug, 11:04 · listed for about 2 h 30 min · no end time published
AthyPlanned · network upgrade
14 customers affected · began Mon 17 Aug, 11:01 · scheduled until 16:30 (5 h 29 min)
MountrathPlanned · supply quality
83 customers affected · began Mon 17 Aug, 09:35 · listed for about 7 h · no end time published
RathdowneyFault
748 customers affected · began Sun 16 Aug, 12:10 · restored 12:38 (28 min) · 1 h 7 min earlier than ESB estimated
Repeat fault - outage 2 of 2 at this location in quick succession
RathdowneyFault
749 customers affected · began Sun 16 Aug, 11:37 · restored 12:08 (31 min) · 1 h 7 min earlier than ESB estimated
Repeat fault - outage 1 of 2 at this location in quick succession
RathdowneyFault
328 customers affected · began Sun 16 Aug, 11:24 · restored 11:37 (13 min) · 1 h 23 min earlier than ESB estimated
RathdowneyFault
825 customers affected · began Sun 16 Aug, 10:36 · restored 11:17 (41 min) · 58 min earlier than ESB estimated
- Outage began · 825 customers
- 209 customers still off
- Supply restored
PortlaoisePlanned · supply quality
186 customers affected · began Sat 15 Aug, 09:03 · listed for about 6 h 30 min · no end time published
RathdowneyFault
1,599 customers affected · began Fri 14 Aug, 17:25 · restored 17:48 (23 min) · 42 min earlier than ESB estimated
PortlaoisePlanned · network upgrade
27 customers affected · began Fri 14 Aug, 14:36 · scheduled until 16:00 (1 h 24 min)
PortlaoisePlanned · line diversion
19 customers affected · began Fri 14 Aug, 11:40 · listed for about 4 h · no end time published
MountrathPlanned · supply quality
12 customers affected · began Fri 14 Aug, 10:26 · listed for about 5 h · no end time published
MountrathPlanned · supply quality
205 customers affected · began Fri 14 Aug, 10:25 · scheduled until 17:00 (6 h 35 min)
MountrathFault
27 customers affected · began Fri 14 Aug, 10:09 · restored 15:40 (5 h 31 min) · 40 min later than ESB estimated
PortlaoisePlanned · network upgrade
57 customers affected · began Fri 14 Aug, 09:37 · listed for about 5 h · no end time published
PortlaoisePlanned · network upgrade
22 customers affected · began Fri 14 Aug, 09:19 · scheduled until 13:00 (3 h 41 min)
MountrathFault
124 customers affected · began Fri 14 Aug, 09:12 · off for about 30 min · no restore time published
RoscreaFault
38 customers affected · began Fri 14 Aug, 09:08 · restored 09:23 (15 min) · 1 h 22 min earlier than ESB estimated
RathdowneyPlanned
1,599 customers affected · began Thu 13 Aug, 17:24 · listed for about 30 min · no end time published
BallyraggetFault
1,000 customers affected · began Thu 13 Aug, 17:24 · restored 18:03 (39 min) · 2 h 42 min earlier than ESB estimated
MountrathFault
227 customers affected · began Thu 13 Aug, 17:24 · restored 18:03 (39 min) · 2 h 42 min earlier than ESB estimated
PortlaoiseFault
16 customers affected · began Thu 13 Aug, 10:43 · restored 15:01 (4 h 18 min) · 29 min earlier than ESB estimated
AthyPlanned
87 customers affected · began Thu 13 Aug, 10:11 · listed for about 6 h 30 min · no end time published
MountrathPlanned
241 customers affected · began Thu 13 Aug, 09:58 · listed for about 6 h 30 min · no end time published
MountrathPlanned
224 customers affected · began Thu 13 Aug, 09:57 · listed for about 6 h 30 min · no end time published
PortlaoiseFault
16 customers affected · began Thu 13 Aug, 07:50 · restored 09:14 (1 h 24 min) · 1 h 16 min earlier than ESB estimated
PortlaoiseFault
604 customers affected · began Thu 13 Aug, 03:59 · restored 04:17 (18 min) · 43 min earlier than ESB estimated
AthyFault
43 customers affected · began Wed 12 Aug, 17:38 · restored 18:59 (1 h 21 min) · 2 h 16 min earlier than ESB estimated
MountmellickPlanned · new connections
33 customers affected · began Wed 12 Aug, 10:20 · listed for about 4 h · no end time published
MountrathPlanned · supply quality
89 customers affected · began Wed 12 Aug, 10:12 · listed for about 6 h 30 min · no end time published
AthyPlanned
170 customers affected · began Wed 12 Aug, 09:07 · scheduled until 16:30 (7 h 23 min)
MountrathPlanned · supply quality
97 customers affected · began Tue 11 Aug, 09:42 · listed for about 6 h 30 min · no end time published
AthyPlanned
176 customers affected · began Tue 11 Aug, 09:12 · listed for about 7 h 30 min · no end time published
AthyPlanned
329 customers affected · began Mon 10 Aug, 10:29 · scheduled until 16:00 (5 h 31 min)
PortlaoiseFault
43 customers affected · began Mon 10 Aug, 10:07 · off for about 1 h · no restore time published
PortlaoisePlanned · supply quality
147 customers affected · began Sat 8 Aug, 10:45 · listed for about 5 h · no end time published
AbbeyleixFault
60 customers affected · began Sat 8 Aug, 00:44 · restored 08:15 (7 h 31 min) · 5 h 45 min earlier than ESB estimated
GraiguePlanned · new connections
106 customers affected · began Fri 7 Aug, 10:07 · listed for about 5 h 30 min · no end time published
RathdowneyPlanned · supply quality
52 customers affected · began Fri 7 Aug, 09:24 · listed for about 5 h · no end time published
MountrathFault
19 customers affected · began Fri 7 Aug, 07:42 · restored 09:40 (1 h 58 min) · 1 h 20 min earlier than ESB estimated
RoscreaPlanned · network upgrade
57 customers affected · began Thu 6 Aug, 09:51 · listed for about 3 h 30 min · no end time published
MountrathPlanned · supply quality
42 customers affected · began Thu 6 Aug, 09:31 · listed for about 7 h · no end time published
PallasPlanned · supply quality
25 customers affected · began Wed 5 Aug, 09:58 · listed for about 6 h · no end time published
PortlaoisePlanned · supply quality
11 customers affected · began Wed 5 Aug, 09:34 · scheduled until 14:00 (4 h 26 min)
MountrathPlanned · supply quality
40 customers affected · began Wed 5 Aug, 09:25 · scheduled until 17:00 (7 h 35 min)
PortlaoisePlanned · line diversion
28 customers affected · began Tue 4 Aug, 10:53 · listed for about 4 h 30 min · no end time published
AthyPlanned · supply quality
40 customers affected · began Tue 4 Aug, 10:23 · scheduled until 16:30 (6 h 7 min)
MountrathPlanned · supply quality
94 customers affected · began Tue 4 Aug, 09:26 · listed for about 5 h · no end time published
MountmellickFault
11 customers affected · began Mon 3 Aug, 22:37 · restored Tue 4 Aug, 00:56 (2 h 19 min) · 19 min earlier than ESB estimated
MountmellickFault
14 customers affected · began Mon 3 Aug, 22:33 · restored Tue 4 Aug, 00:56 (2 h 23 min) · 11 min later than ESB estimated
MountmellickFault
12 customers affected · began Mon 3 Aug, 22:31 · restored Tue 4 Aug, 00:55 (2 h 24 min) · 10 min later than ESB estimated
RoscreaFault
28 customers affected · began Mon 3 Aug, 21:03 · restored Tue 4 Aug, 00:09 (3 h 6 min) · 21 min earlier than ESB estimated
MountmellickFault
1,660 customers affected · began Mon 3 Aug, 20:15 · restored Tue 4 Aug, 15:18 (19 h 3 min) · 42 min earlier than ESB estimated
- Outage began · 1,660 customers
4 further updates
- 764 customers still off
- 633 customers still off
- 347 customers still off
- 32 customers still off
- Supply restored
AbbeyleixFault
34 customers affected · began Sat 1 Aug, 13:48 · restored 15:31 (1 h 43 min) · 44 min earlier than ESB estimated